Construction Management: CPM Scheduling Basics
Identify the critical path and project duration from a simple activity network.
Practice Questions
Q1.In a CPM network, Activity A (3 days) must finish before Activity B (4 days) and Activity C (2 days). B and C must both finish before Activity D (1 day). What is the critical path duration?
Q2.An activity on the critical path has float (slack) of:
Q3.Float (or slack) is best defined as: